Exterior tiling

Dutka Ákos St. — Terrace, staircases and full exterior tiling

270 m²+ full tile replacement around the house and garage. Two new terraces with earthwork and reinforced concrete foundation, two staircase flights, facade and side cladding.

Tiling area
270+ m²
Project value
20 M Ft
Duration
3 months
Location
Budapest
Dutka Ákos — exterior tiling, completed work
Dutka Ákos — terrace tiling
Dutka Ákos — staircase flight tiling
Dutka Ákos — facade tiling
Dutka Ákos — garage facade
Dutka Ákos — side tiling
Dutka Ákos — staircase detail
Dutka Ákos — completed terrace
Completed terrace with large-format stone tiles and brick retaining wall — Dutka Ákos u. Budapest exterior tiling
Completed terrace and garden with brick wall and steps — Dutka Ákos u. Budapest paving

During construction

Dutka Ákos — concrete base pouring
Dutka Ákos — reinforcement mesh application
Dutka Ákos — tiling process
Dutka Ákos — work in progress
Dutka Ákos — work in progress 2
270+
m² tiles total
2
staircase flights
3
months construction
20M
Ft contract value

The project

Full exterior tile replacement around the house and garage — from demolition of old surfaces to handover of two new terraces. The project included land grading, reinforced concrete foundation pouring for two terraces, two staircase flights, and complete tiling of the house and garage facades and side elevations.

Scope of works

  • Full demolition and removal of old tile surfaces
  • Earthwork — land grading and levelling
  • Reinforced concrete foundation for two terraces
  • Two staircase flights — tiling on all surfaces
  • Full facade tiling of house and garage
  • Side surface cladding — 270+ m² tiles total
  • Decorative retaining wall against soil erosion — clad with clinker brick

Challenges and solutions

The most critical element was the reinforced concrete foundation: the terrace required a stable, frost-resistant base, demanding thorough site assessment and precise formwork. For the staircase flights, we paid special attention to drainage and waterproof grouting to prevent frost damage from water infiltration.

Construction process

3 months, 5 phases

01
Demolition
Old tile removal, disposal
02
Earthworks
Grading, foundation prep
03
Foundation
Reinforced concrete, formwork
04
Staircases
Two flights, tiling
05
Facade
House and garage full tiling